From concept to completion, Lotus Hospitality Products delivers excellence through our comprehensive six-stage process. With over 50 years of expertise, we partner with leading hotels worldwide, managing every aspect from initial design and material selection to manufacturing and final delivery. Our process ensures quality, timeliness, and complete client satisfaction at every step.

Contact Us
Lotus process illustration

How We Work

Each of these steps is crucial to ensure that the final product is of high quality and meets customer expectations. If you have any specific questions about a particular aspect of the manufacturing process, feel free to ask!

Our Process 

Process Details
  1. Design and Development

    This is where the product concept is created and refined. It involves research, prototyping, and testing to ensure the product meets all necessary specifications and standards.

  2. Sourcing Materials

    Once the design is finalized, the necessary raw materials and components are sourced from suppliers. This step involves negotiating with suppliers, ensuring quality, and managing logistics.

  3. Production Planning

    This involves scheduling the production runs, allocating resources, and ensuring that all necessary equipment and personnel are available.

  4. Manufacturing

    This is the actual production phase where raw materials are transformed into finished products. It can involve various processes such as machining, assembly, welding, and quality control.

  5. Quality Control

    Throughout the manufacturing process, quality control measures are implemented to ensure that the products meet the required standards. This can involve inspections, testing, and adjustments to the production process.

  6. Packaging and Distribution

    Once the products are manufactured and pass quality control, they are packaged and prepared for distribution. This step involves labeling, packaging, and shipping the products to customers or retailers.

Ordering Process and Procedures

For producing quotes and accepting orders for casegoods, seating, atrwork, mirror, and lighting requests.

Download Form

Status

Description

Typical Timing

Yes/No

Has the client submited conceptual ideas, images, sketches, photo or drawings? Has the client provided pictures of specific product they are interested in?

2-3 days

Yes/No

Has Lotus began with sketching ideas and researching options in conjunction with the designer base on their product & budget? If an image has been provided, pricing typically happens within 24-48 hours.

2-3 days

Note

After final approval of estimate and purchasing has been decided, a deposit is required to have the order entered into production. Lotus then initiates line drawings based on the quoted measurements,

dimensions, material finishes, and decorative details; this takes 3-5 working days

2-3 weeks

RECEIVED?
Yes/No

Line drawings are sent to the rep and or client for approval, once the signed off drawings are received the order is staged for production.

3-5 days

RECEIVED?
Yes/No

Fabric, wood and metal samples are sent for approval; 2-3 weeks to receive samples

2-3 weeks

RECEIVED?
Yes/No

Once the final set of line drawings are approved, a sample is produced for client to review and approve, this is done prior to going to mass production. 3-4 weeks

3-4 weeks

Note

Once production is started, orders typically take 45-60 days production

5-6 weeks

Note

The factory sends an inspection report with pictures, video of each item fully assembled, the order is then packed and loaded on the container

2-3 days

Completed
Yes/No

Once inspection have been reviewed and approved by the client, LHP requires final payment before the container leaves the port.

1-2 weeks

Note

Crates are labelled with product type, picture and installation instructions.

3-5 days

TBD

It is pre-determined which mode of transportation suits the clients needs; i.e. MOST EXPENSIVE / Air freight (10 to 15 days) , EXPENSE GREATER than standard / Fast Boat only available for China shipments (22 to 29 days) or STANDARD / Via ocean (50 to 60 days). These modes of transportation can be changed up until 2-3 days before product leaves port.

50-60 days

Note

Products are passed through Overseas Customs and US Customs.

2-3 days

Note

Once cleared by customs, the freight forwarder calls the client and the client is given a heads up on a delivery date and time of ETA to the job site and or delivery address provided to on the PO. (Our team can be there to assist you and your client )

2-3 days

** Life Cycle of project **
22 weeks to 12 weeks
However, if the timing of the tasks above are reduced, the project life cycle can be less.